Nualux II’s official registrations in Portugal, the CE marking process for its control panels and the instrument used for its test reports.
Nualux II’s registrations in Portugal, its PME Líder 2026 status and the tests carried out with its HT Italia FULLTEST3. Where a certificate or registration number is still being confirmed, this is indicated.
Installer registered with the Directorate-General for Energy and Geology (DGEG) to carry out electrical installations in Portugal.
Registered with the National Authority for Emergency and Civil Protection (ANEPC) for fire safety work.
Nualux II builds main switchboards and low voltage control panels in its own workshop and applies CE marking after individual routine verification to EN 61439-1 and EN 61439-2.
PME Líder 2026 status awarded by IAPMEI in partnership with Novo Banco, based on financial performance and credit rating.
Nualux II works with Siemens equipment and collaborates with Siemens on port projects.
Nualux II tests the control panels built in its workshop, as well as the machines and installations it wires on site, with an HT Italia FULLTEST3 multifunction tester. The instrument covers the safety tests of EN 61439-1 and EN 61439-2 for switchgear assemblies and of EN 60204-1 for the electrical equipment of machines.
Besides insulation, continuity and dielectric strength tests, it measures residual voltage discharge time, phase sequence and earth resistance without tripping RCDs. The results go into the test report handed over at site acceptance.

Test at 100, 250, 500 or 1000 V DC between live conductors and the equipotential protective circuit, with the result in megohms.
Test at 200 mA and at 10 A or 25 A, measured on enclosures, doors, mounting plates and machine frames.
AC withstand voltage test, programmable from 250 V to 5100 V, on panels and machine equipment, to EN 61439 and EN 60204-1.
Measurement of trip time and trip current of type AC, A and B residual current devices on distribution circuits.
Measurement of line and fault loop impedance, with calculation of the prospective short-circuit current to verify that protective devices disconnect in time.
Measurement without tripping the installed RCDs, on site installations, transformer substations and lightning protection test joints.
Insulation resistance testing identifies degraded cable insulation, moisture and conductive contamination between live conductors and earth, or between phases, before they cause a fault.
The team isolates and locks off the circuit, verifies the absence of voltage and disconnects surge protective devices, PLCs and variable speed drives so the DC test voltage cannot damage them. With the FULLTEST3 it applies 250, 500 or 1000 V DC according to the rated voltage of the circuit and records the stabilised value in megohms for each line.
Each line of the test sheet shows the circuit, the test voltage applied, the measured value and the minimum reference value required by the standard that applies to the installation.

Each report identifies the circuit, the test carried out, the instrument used and its serial number, the result obtained, the date and the technician who performed the test.

The team isolates the control panel and disconnects the PLCs, surge protective devices and variable speed drives so the DC test voltage is not applied to them. It then applies 250, 500 or 1000 V DC according to the circuit voltage and records the value in megohms for each circuit.
Yes. The FULLTEST3 has an earth resistance function that does not trip the installed RCDs. On transformer substations and lightning protection systems, Nualux II also measures at the removable test joints with auxiliary earth stakes.
DGEG registration legally authorises a company to carry out electrical installations in Portugal within its assigned category. ANEPC registration covers fire safety work in buildings.
Yes, Nualux II issues test reports and technical documentation for control panels in English. A sample can be requested before placing an order.

Motor control centres (MCC), PLC panels and power panels, tested and CE marked before shipping.

Preventive maintenance plans, thermal imaging and breakdown support.

Construction and annual maintenance, with oil analysis and earth resistance testing.

Ask for a sample test report and the Nualux II registration details at nualux@nualux.pt.