Fire detection for factories and warehouses. Nualux installs the power supply, cable trays, loop cabling, detectors and control panel, and commissions the system.
An automatic fire detection system detects smoke and heat and raises the alarm through a control panel before the fire spreads.
Nualux electricians install the power supply, cable trays and fire-resistant cabling for the detection loops, mount the detectors and manual call points, program the control panel and commission the system.
Three groups of equipment, connected by cabling that has to keep working during a fire.
Receives the signals from every device, identifies the zone and triggers the alarm and safety controls. It has its own standby batteries.
Ceiling-mounted smoke and heat detectors and manual call points next to the exits, spread across detection zones.
Sounders and visual alarm devices that warn people and can trigger smoke vents to open or equipment to stop.
Dedicated, protected circuit for the fire detection control panel and its standby batteries.
Fire-resistant cable fixed along roof trusses, cable trays and steel structures, with suitable supports.
Cable runs for detectors, manual call points and sounders in every detection zone.
Control panel programming, testing of every alarm sequence and commissioning of the system.
Measurement of continuity, insulation and earthing of the installation with the HT Fulltest3.
Maintenance visits recorded in the fire safety file.
The Portuguese fire safety regulations for buildings require anyone who sells, installs or maintains this equipment to be registered with the National Authority for Emergency and Civil Protection (ANEPC).
Legal framework: Decree-Law no. 220/2008 (article 23), Ordinance no. 1532/2008 (technical regulation) and Ordinance no. 773/2009.
Nualux hands over the test results, loop drawings and manuals, for the fire safety file and for the inspection.
The team reviews the building plans, ceiling heights, fire compartments and production areas to define the cable routes.
The team installs the power circuits, the cable trays and the detection loop cables.
The team mounts the detectors, programs the control panel and tests every alarm sequence.
Test results, loop drawings and manuals are handed to the client's team for the inspection and for the fire safety file.






The job ends with the documents that go into the site’s fire safety file.
Continuity, insulation and earthing of the circuits measured with the HT Fulltest3.
Route of each loop, with the location of detectors, call points and sounders by zone.
Maintenance work, tests and incidents recorded for review at the inspection and audits.
The systems usually installed at the same time.
Make your first contact here for a quote. No obligation.
The system uses smoke and heat detectors and manual call points connected to a fire detection control panel. When a device activates, the panel raises the alarm and can trigger other safety actions, such as opening smoke vents or stopping equipment.
It is the series of European standards for the components of fire detection and alarm systems: control panels, power supplies, detectors, manual call points and sounders. It sets the performance and test requirements this equipment must meet.
Companies registered with ANEPC for the sale, installation or maintenance of fire safety equipment. Nualux is registered with ANEPC and carries out the full installation: electrical work, detector installation and control panel programming.
It depends on the building’s use type, its risk category and the technical fire safety regulations. Many factories connect the control panel to an alarm receiving service so the alert goes out even when nobody is on site.
Circuits that must keep working during a fire use fire-resistant cable, fixed with supports that also resist fire, so signals and alarms keep reaching the control panel and the sounders.
It depends on the floor area, ceiling height, number of detection zones and the constraints of the plant’s operation. Nualux provides a schedule after reviewing the plans.
The system needs periodic maintenance to test detectors, manual call points, sounders, standby batteries and control panel functions. The interval is set by fire safety legislation and by the design, and every action is entered in the safety records.